Group Home About LGH Group Catalogue Request Enquiries  
 
Hoisting
Pulling & Winching
General Tackle
Safety Equipment
Jacking
Cable Handling
Access & Handling
Man Riding
Load Measurement
Power Packs
Hire
Sales
Service
Manufacture
Training
Testing
Installation
Calibration
Tackle Store

The LGH MEGALIFT team was called upon to use its flair and creativity to devise a solution for a problem involving a tanker of dangerous chemicals. The tanker, which had become bonded to its trailer, needed to be moved to a safe place for disposal.

The chemicals were extremely flammable, and as such the whole building had to be cocooned to create a safety bubble. This created difficulties in lifting the vessel. Health and safety officers in charge of the area would not sanction the removal of any of the protective cocoon during the lifting of the vessel; this greatly reduced the options open the engineers.

The MEGALFT team was brought in to assist with the safe removal of the vessel and initially carried an engineering study and risk assessment. From this they created a novel solution to the problem.

The MEGALIFT tracks were laid, travelling from outside the protective sheeting through and up to the vessel. The MEGALIFT jacking legs were erected on the tracks outside the protective sheeting. 12 metre lifting beams were fitted to the MEGALIFT system creating two long arms with which to lift the vessel. To counter balance the weight of the vessel during lifting, 20t of ballast was attached to the rear of the system.

It was agreed that the vessel needed to be lifted at se veral points while monitoring the load, to ensure the integrity of the vessel and the safe handling of the chemicals. Several slings were therefore passed around the body of the vessel. At each lifting point a Load Shackle was attached enabling the loading to be monitored accurately.

The MEGALIFT system was moved along its tracking until the slings could be attached to the lifting beams by means of lever hoists. The vessel was then removed from the building by reversing the MEGALIFT system along its tracks. Plastic sheeting was placed over the vessel as it emerged to protect it from the elements.

Everyone was extremely pleased that the potentially dangerous vessel had been removed safely thanks to the care and creativity applied by the MEGALIFT team.

 
Bridge Lifting
Machine Moving
Creativity
Experience
Versatility
Knowledge
Expertise
Problem Solving
 
 
Click heer to order brochures
Request Information
ISO 9001 Members of the Lifting Equipment Engineers Association Full Members of SAEMA A Member of the Northern Offshore Federation  
LGH GROUP HOMEPAGE